Purpose |
.Net App for Generating a file for work order confirmations |
Release No |
001 |
Submitted on |
07/01/2015 |
Submitted by |
Adithya |
Environment |
DEV to QAS |
Sent To |
Jeffrey Mau, JIngsha |
Object(s) created by |
Vamshi, Venkat |
Object(s) tested by |
Adithya |
Transport Status |
Transports are there in SND 100 |
Sl. |
Transport ID |
Description |
Object Name |
1 |
SNDK900446 |
SNC:16728 - Add Link to .Net Work order process |
/SCF/UNAVCFG |
2 |
SNDK900444 |
SNC:16728 - Work Order File Download and .Net Link |
ZGET_SELECTION_POST ZNEC_PRE_MENU_ITM_CLICK ZNEE_EN008_IE_WODWLD_1 ZWO_PO_LINE |
Test ID |
Test Scenario |
Expected Results |
Actual Results |
P/F |
Documents |
Notes |
Tested |
QA By |
.Net Application functionality testing Individually |
||||||||
---|---|---|---|---|---|---|---|---|
SCM1 |
Full End to End Cycle with combination of two vendors. |
End to End - Download & Upload must be done correctly. |
End to End - Download & Upload is processed successfully with confirmations updated CUT, EMB & SEW |
P |
Download files Sent to .Net: 202663: CUST_NEC_WOACT_20150701093107.csv 202666: CUST_NEC_WOACT_20150701093123.csv Received Files (updated with confirmations) 202663: CUST_NEC_WOACT_CONFIRMATION_20157120345.csv 202666: CUST_NEC_WOACT_CONFIRMATION_20157120289.csv |
END to END is done with Pos 4500075379, 4500075373, 4500075369 4500075365 4500075383 |
Adithya |
Adithya |
SCM2 |
Download all upload only changed work orders |
The File which generated for uploading confirmations must have the WOs which are updated with the confirmations. On Uploading the file the confirmations must be updated. |
The File generated from .Net app is generated with changed work orders and after uploading it in Upload Center the confirmations have been updated successfully for those Work orders for which confirmations is updated. rest of the Work orders are not effected. |
P |
4500075379 4500075373 4500075369 Updated Work orders for Po's 4600008425, 4600008427, 4600008428 - File has is received with these Po's In DEV seen that Work order count is 104.080 before download and after upload. |
Adithya |
Adithya |
|
SCM3 |
Download the Wo with CNCL status and upload it and see if other work orders are updated with the status |
The work orders other than the CNCL must be updated with confirmations |
The work orders other than the CNCL are updated with confirmations |
The File which is uploaded is ended with errors but the other work orders which are not with the CNCL status are updated with respective confirmations |
Adithya |
Adithya |
||
SCM4 |
Validate if the ML Work orders are seen in EB (Update EB Wo from ML app screen) |
No EB POs Work Orders shall be seen in the ML Screen and vice versa |
EB Work Orders are not seen in ML Application |
P |
EB PO is not shown up in ML Screen - 4500075379 |
Adithya |
Adithya |
|
SCM5 |
Upload the file which has transport phase updated already but no COM status. |
COM Shall be updated though Transport is updated with out deleting the existing updated in TRANSPORT |
COM status is updated correctly with the upload file though TRANSPORT is already updated. |
P |
4500075350 File Sent: CUST_NEC_WOACT_20150701123534.csv File Received: CUST_NEC_WOACT_CONFIRMATION_20157122100.csv. |
Adithya |
Adithya |
|
SCM6 |
Once the download is clicked - no changes shall be allowed |
No Changes shall be allowed after Download is clicked from .Net Application |
||||||
Download file Testing |
||||||||
SCM7 |
If any one line (WO) of a PO is active ( not updated with COM) |
All the work orders of that PO are to be downloaded in the file |
CUST_NEC_WOACT_CONFIRMATION_201571084225.csv |
|||||
SCM8 |
If any Work orders of the PO are not even updated with any one phase |
All the work orders must be downloaded in the file |
All work orders are downloaded in the file |
P |
4600008588 4600008587 |
Adithya |
Adithya |
|
SCM9 |
If all work orders of the PO are updated with COM |
No work orders of the PO must be downloaded in the file |
No work orders are downloaded in the file |
P |
4600008594 |
Adithya |
Adithya |
|
SCM10 |
If Work orders of the PO lines are mix of Open, Closed & Complete |
All the work orders must be downloaded in the file |
All work orders are downloaded in the file |
P |
4600008590 |
Adithya |
Adithya |
|
SCM11 |
If the work orders of the PO are mixed with One WO not updated any phase, Two Work Orders updated with all phases & One Work Order updated with 2 phases |
All the work orders must be downloaded in the file |
All work orders are downloaded in the file |
P |
4600008591 |
Adithya |
Adithya |
|
SCM12 |
Download the file wide open |
All the Open POs and its corresponding Work orders must be downloaded in the file |
All the Open POs and its corresponding Work orders are downloaded in the file |
P |
Adithya |
Adithya |
||
.Net Application Screen testing |
||||||||
SCM13 |
Un Check functionality |
We should be able to uncheck the confirmation flag |
We were able to uncheck the confirmation flag |
P |
Adithya |
Vamshi |
||
SCM14 |
On hitting Day End process |
A file will be generated/downloaded with the work orders for which the confirmations are updated. |
A file is generated/downloaded with the work orders for which the confirmations are updated. |
P |
Adithya |
Vamshi |
||
.Net Application Link testing |
||||||||
SCM15 |
If we hit Simple WO List under Reports |
.Net application page shall be opened with the vendor which a user is logged in |
.Net application page is opened with the vendor which a user is logged in |
P |
Adithya |
Adithya |
||
File2 to .Net Application |
||||||||
SCM16 |
Execute the Program ZWO_PO_LINE Wide Open |
A file must be generated with all the work orders of all the vendors and placed in the defined path of the application server AL11 in SND |
A file is generated with all the work orders of all the vendors and placed in the defined path of the application server AL11 in SND |
P |
Adithya |
Adithya |
Test ID |
Test Scenario |
Expected Results |
Actual Results |
P/F |
Documents |
Notes |
Tested by |
QA by |
SCM1 |
Full End to End Cycle with combination of two vendors. |
End to End - Download & Upload must be done correctly.Validation Reports-
|
End to End - Download & Upload are done.
|
P |
1. a) POs which are Complete are not downloaded in the download file 4500073821, 4500073849, 4500073851. b) Mix of complete and Inprocess lines of a PO 4500073850 2) Count from the upload file: 202663: Total Records: 36948, Purchase Orders: 183 Work Orders: 1420 202666; Total Records: 62476, Purchase Orders: 594 Work Orders: 2840 3. Update CUT & EMB for POs 202663: 4500075520, 4500075407 202666: 4500074877 4500074878 4. Update CUT & EMB for POs 202663: 4500075520, 4500075407 202666: 4500074877 4500074878 |
Downloaded file from Download Center Vendor: 202663 cust_nec_woact_20150717092232.csv Vendor 202666cust_nec_woact_20150717092511.csv Day End Process file from the .Net Application. Vendor 202663 CUST_NEC_WOACT_CONFIRMATION_2015717121016.csv Vendor 202666 CUST_NEC_WOACT_CONFIRMATION_2015717124344.csv |
Adithya |
Venkat |
SCM2 |
Execute scenarios with multiple upload/download cycles to ensure Work Orders statuses are updated correctly in SNC after each receipt from .NET |
WO confirmations in SNC after each cycle should be correct. ECC idoc confirmations should be correct |
WO confirmations in SNC after each cycle are correct. ECC idoc confirmations are correct |
First uploaded file from the .Net application: CUST_NEC_WOACT_CONFIRMATION_2015717151417.csv updated few more work orders and Re hit Day End Process: CUST_NEC_WOACT_CONFIRMATION_2015717151417.csv |
||||
SCM3 |
Download all upload only changed work orders |
The File which generated for uploading confirmations must have the WOs which are updated with the confirmations. On Uploading the file the confirmations must be updated. |
The File which generated for uploading confirmations are having only the WOs which are updated with the confirmations. On Uploading the file the confirmations must be updated. |
P |
The data which is modified are only triggered in the Day End process file from .Net application, the rest of the work orders are unchanged in the SNC. |
Above uploaded Files can be taken as the examples. |
Adithya |
Venkat |
SCM4 |
Download the Wo with CNCL status and upload it and see if other work orders are updated with the status |
The work orders other than the CNCL must be updated with confirmations |
The Work orders other than the CNCL status are updated with the confirmations and the WO with CNCL are not updated and set an Error message. |
P |
Attached is the file "Day End Process" with the confirmations updated. CUST_NEC_WOACT_CONFIRMATION_2015717144253.csv Attached is the list of work orders updated when a Work Order is with CNCL is updated export_20150717145238.xls |
PO: 4500075495 Work Orders; W300003368 & W300003369 |
Adithya |
Venkat |
SCM5 |
Security check- User will try to enter PO which may or may not be part of their company |
No EB POs Work Orders shall be seen in the ML Screen and vice versa |
No EB POs Work Orders are seen in the ML Screen and vice versa |
P |
PO 4500075493 is not shown in 202663 URL and 4500075487 is not shown up in the 202666 URL. |
Adithya |
Venkat |
|
SCM6 |
Upload the file which has transport phase updated already but no COM status. |
COM Shall be updated though Transport phase is updated with out deleting the existing updated in TRANSPORT |
COM phase is updated though Transport phase is updated with out deleting the existing updated in TRANSPORT |
P |
PO 4500075518, ASN is Published and Transport phase is updated for all the Work Orders of the PO. Updated COM from the .Net application and COM status is updated in the corresponding Work Orders of the PO. |
Adithya |
Venkat |
|
SCM7 |
Load Testing Upload Confirmations to Find Time |
The phases updated from the .Net Application are to be updated with the upload of the Day end process file in upload center of SNC. |
The phases updated from the .Net Application are updated with the upload of the Day end process file in upload center of SNC. |
P |
Uploaded 1114 Work orders and it took 25 mins in SNC |
Here is the file attached which is uploaded CUST_NEC_WOACT_CONFIRMATION_201572013267.csv |
Test ID |
Test Scenario |
Expected Results |
Actual Results |
P/F |
Documents |
Notes |
Tested by |
QA by |
001 |
Enter PO number and click on Apply |
The work order details for the PO will be displayed in the grid |
The work order details for the PO are displayed in the grid |
P |
Vamshi/ Adithya |
Venkat |
||
002 |
Update the confirmations for the Phases by check and unchecking the check boxes and save |
User should be able to check and uncheck the check boxes for the phase completed and the data should be saved to database on Save click |
Check and Un Check functionality is working and the data is saved after SAVE button is hit. |
P |
Vamshi/ Adithya |
Venkat |
||
003 |
Day End Process |
User should be able to download the updated confirmations. |
When Hit "Day end Process" the file is downloaded from application with the updated POs |
P |
Vamshi/ Adithya |
Venkat |
||
004 |
Ensure all Open PO Lines Received |
All Open POs shall be received in the downloaded file and in to the .Net application |
All Open POs are received in the downloaded file and in to the .Net application |
P |
Vamshi/ Adithya |
Venkat |
Test ID |
Test Scenario |
Expected Results |
Actual Results |
P/F |
Documents |
Notes |
Tested by |
QA by |
DC001 |
Run the Download file Job 1. If any one line (WO) of a PO is active ( not updated with COM) 2. If No Work orders are updated with any phase of the PO. 3. If all work orders of the PO are updated with all Phases till COM 4. If Work orders of the PO lines are mix of Open, Closed & Complete |
A file shall be placed in the application server. 1. All the work orders of that PO must be downloaded in the file. 2. All the work orders of that PO must be downloaded in the file. 3. No Work orders of that PO must be downloaded in the file. 4. All the work orders of that PO must be downloaded in the file. |
Files are placed in the application server. 1. All the work orders of that PO are in downloaded in the file. 2. All the work orders of that PO are downloaded in the file. 3. No Work orders of that PO are downloaded in the file. 4. All the work orders of that PO are downloaded in the file. |
P |
1. 4500074459 2. 4500074451 3. 4500075074 . 4. 4500075485 |
Master list is a list which is having the list of all Open & Closed POs. MasterList_QAS.xls Downloaded file from SNC: 202663 cust_nec_woact_20150714122741.csv 202666 cust_nec_woact_20150714122129.csv |
Adithya |
Venkat |
DC002 |
Download the file wide open |
All the Open POs and its corresponding Work orders must be downloaded in the file |
All the Open POs and its corresponding Work orders are downloaded in the file |
P |
Consider the above uploaded file. |
Adithya |
Venkat |